REBID - Bakersville 2016 Water System Improvements (20160062.00.CL)

The project involves system wide improvements to the Town’s existing water supply and distribution system and consists of three (3) divisions of work with the following general scope:

Division 1 – New Water Supply Well Development: The development of a new groundwater supply well and rehabilitation of an existing groundwater supply well that has been abandoned due to dimensioned yield. The new groundwater supply well has been drilled and evaluated and was determined to be suitable of use as a public water supply source. The well was secured and work under this contract is to complete its development by installing the pump and piping, constructing an enclosure, providing electrical mechanical equipment and other appurtenances, and connecting to the existing distribution system via approximately 1,350 LF of 6-inch watermain.

Division 2 – Watermain Replacement and Improvements: Replacement of existing deteriorated water lines, with new 2-inch and 6-inch diameter water lines, where specified on the Drawings, abandonment of existing watermain sections which are being replaced, and installation of new service taps with meter, meter box and setting equipment, along new watermain sections. Installation of water mains shall be via open-cut and trenchless methods as specified. This work includes trenchless installation of a small diameter watermain under a DOT roadway and stream. This work consists of installing approximately 4000 LF of new and replacement water main with 2 and 6-inch PVC and DIP.

Division 3 – Water Service Improvements and Meter Replacement: Replacement of existing non-copper water service lines from the water main to the edge of right-of-way and the relocation of water meters to the edge of the right-of-way. Selective replacement of water service from the meter location to the house or structure, which may also require modification of internal building plumbing, and; Furnishing and installing approximately 300 new water meters (3/4” residential and 2” commercial), complete with setting equipment and meter boxes. Meter replacement work includes providing all services necessary for meter reading data preservation and integration into the Town’s billing records.

           Place Order 
You must log in to view these files.

If you do not already have an account, you can freely register for one by going here.